Bond Accountability
NCTPA Hybrid Bus Purchase |
|
Description: Project is to fund the purchase of one (1) gasoline/electric hybrid bus (out of 4 bus procurement)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Napa |
| City | Napa |
| Zip Code | 94559 |
| Senate District |
02 |
| Assembly District | 07 |
| Congressional District | |
| Caltrans District |
04 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Reduce Emissions (percent) | ||
| Reduced Emissions | ||
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
Napa County Transportation and Planning Agency | Tracy Geraghty | (707) 259-8779 | tgeraghty@nctpa.net |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $13 | $13 | ||||
| PTMISEA-99313 |
$300 | $0 | $300 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$2,518 | $-1,239 | $1,279 | ||||
| Local** |
$0 | $113 | $113 | ||||
| Total**** | $2,818 | $-1,113 | $1,705 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$2,818 | $-1,113 | $1,705 | $1,705 | $1,705 | $0 | |
| Total* | $2,818 | $-1,113 | $1,705 | $1,705 | $1,705 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/01/2002 07/31/2008 |
04/14/2009 04/14/2009 |
03/01/2002 11/16/2008 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
09/01/2007 06/01/2008 |
03/16/2010 03/16/2010 |
01/01/2008 07/01/2009 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
06/01/2008 12/01/2008 |
03/16/2010 03/16/2010 |
06/01/2009 06/30/2009 |
0 | |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Reduce Emissions (percent) | ||
| Reduced Emissions | ||
| Bond Funding Cost | |
|---|---|
| Adopted: |
$300,170 |
| Current Approved: |
$300,170 |
| Actual Expenditures: |
$300,170 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31