| TART Operations Center Computer Server | 
| Description: Provide reliable link between TART oper. & admin. center | 
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County | Placer | 
| City | Auburn | 
| Zip Code | 95603 | 
| Senate District | 01 | 
| Assembly District | 04 | 
| Congressional District | 04 | 
| Caltrans District | 03 | 
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increase System Reliability (percent) | ||
| Useful Life (years) | 5 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA | Placer County Dept. of Public Works | Will Garner | (530) 745-7582 | wgarner@placer.ca.gov | 
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a | Approved Changes (06/30/2025 b=c-a | Current Approved (06/30/2025 c | |||||
| Bond Funding | |||||||
| PTMISEA-Interest | $0 | $1 | $1 | ||||
| PTMISEA-99313 | $0 | $3 | $3 | ||||
| PTMISEA-99314 | $19 | $0 | $19 | ||||
| Non-bond Funding | |||||||
| Total**** | $19 | $4 | $23 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a | Approved Changes (06/30/2025 b=c-a | Current Approved (06/30/2025 c | Cost to Date** (06/30/2025 d | Cost Forecast (06/30/2025 e | Cost Variance f=c-e | ||
| Environmental | $0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) | $0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way | $0 | $0 | $0 | $0 | $0 | $0 | |
| Construction | $19 | $4 | $23 | $23 | $23 | $0 | |
| Total* | $19 | $4 | $23 | $23 | $23 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a | Approved Changes (mm/dd/yyyy) b | Current Approved (06/30/2025) c | % Complete (06/30/2025) d | Schedule Forecast (06/30/2025) e | Schedule Variance (months) f=c-e | 
| Begin Environmental Phase End Environmental Phase |  |  |  | 0 |  | 0 0 | 
| Begin Design (PS&E) Phase End Design (PS&E) Phase | 06/01/2008 | 09/23/2008 | 12/01/2008 | 0 |  | 0 0 | 
| Begin Right of Way Phase End Right of Way Phase |  |  |  | 0 |  | 0 0 | 
| Begin Construction Phase End Construction Phase | 06/01/2008 10/01/2008 | 10/07/2009 10/07/2009 | 05/01/2009 06/30/2009 | 100 |  | 0 0 | 
| Begin Closeout Phase End Closeout Phase |  | 10/07/2009 10/07/2009 | 07/01/2009 07/31/2009 | 0 |  | 0 0 | 
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increase System Reliability (percent) | ||
| Useful Life (years) | 5 | |
| Bond Funding Cost | |
|---|---|
| Adopted: | $19,094 | 
| Current Approved: | $22,266 | 
| Actual Expenditures: | $22,266 | 
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31