Description: Expand services - Diesel Multiple Unit (DMU) passenger rail system
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
San Diego |
| City | Oceanside |
| Zip Code | 92054 |
| Senate District |
38 |
| Assembly District | 73, 74, 75 |
| Congressional District | 50 |
| Caltrans District |
11 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Additonal Rail Miles | 22 | |
| Increase System Reliability | ||
| Increased Ridership | 17 | |
| Number of New Rail Cars Purchased for Expansion | 12 | |
| Useful Life (years) | 25 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
North San Diego County Transit District | Daine Hessler | (760) 966-6550 | dhessler@nctd.org |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99313 |
$6,167 | $0 | $6,167 | ||||
| PTMISEA-99314 |
$2,436 | $0 | $2,436 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$266,800 | $97,093 | $363,893 | ||||
| Local** |
$135,692 | $-30,560 | $105,132 | ||||
| Total**** | $411,095 | $66,533 | $477,628 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$17,560 | $0 | $17,560 | $15,666 | $15,666 | $1,894 | |
| Right of Way |
$48,616 | $0 | $48,616 | $95,803 | $95,803 | $-47,187 | |
| Construction |
$344,919 | $66,533 | $411,452 | $366,158 | $366,158 | $45,294 | |
| Total* | $411,095 | $66,533 | $477,628 | $477,628 | $477,628 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
05/01/1989 06/01/1991 |
|
05/01/1989 06/01/1991 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/1994 09/01/2005 |
|
04/01/1994 09/01/2005 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
12/01/1987 09/01/2005 |
|
12/01/1987 09/01/2005 |
100 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
11/01/2002 04/01/2008 |
|
11/01/2002 04/01/2008 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
10/01/2007 12/01/2008 |
|
10/01/2007 12/01/2008 |
100 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Additonal Rail Miles | 22 | |
| Increase System Reliability | ||
| Increased Ridership | 17 | |
| Number of New Rail Cars Purchased for Expansion | 12 | |
| Useful Life (years) | 25 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$8,602,925 |
| Current Approved: |
$8,602,925 |
| Actual Expenditures: |
$8,602,925 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31