Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bus Replacement |
|
Description: Purchase two 35-ft CNG buses
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Tulare |
| City | |
| Zip Code | |
| Senate District |
18 |
| Assembly District | 34 |
| Congressional District | |
| Caltrans District |
06 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 15 | |
| Increased Ridership | 15 | |
| Number of Buses Purchased for Replacment | 2 | |
| Reduced Emissions | 15 | |
| Useful Life (years) | 10 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
CIty of Tulare | Darlene Thompson | 559-684-4227 | dthompson@ci.tulare.ca.us |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $18 | $18 | ||||
| PTMISEA-99313 |
$439 | $0 | $439 | ||||
| PTMISEA-99314 |
$20 | $0 | $20 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$121 | $-121 | $0 | ||||
| Local** |
$0 | $324 | $324 | ||||
| Total**** | $581 | $221 | $801 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $801 | $801 | $-801 | |
| Construction |
$581 | $221 | $801 | $0 | $0 | $801 | |
| Total* | $581 | $221 | $801 | $801 | $801 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
04/01/2008 06/10/2009 |
09/23/2009 09/23/2009 |
08/01/2009 09/01/2009 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
06/01/2010 |
05/20/2010 |
06/01/2010 |
100 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 15 | |
| Increased Ridership | 15 | |
| Number of Buses Purchased for Replacment | 2 | |
| Reduced Emissions | 15 | |
| Useful Life (years) | 10 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$459,641 |
| Current Approved: |
$459,641 |
| Actual Expenditures: |
$459,641 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31
