Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Design, R/W Acquis & Const of a Visitor/Shuttle Info Center |
|
Description: Design, RW & Const. Of Visitor Center/Shuttle Informantion office with additional parking
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Tulare |
| City | |
| Zip Code | |
| Senate District |
18 |
| Assembly District | 34 |
| Congressional District | |
| Caltrans District |
06 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase in Ridership (percent) | 50 | |
| Useful Life (years) | 50 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
CIty of Visalia Transit District | Monty Cox | 559-713-4100 | transit@ci.visalia.ca.us |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $9 | $9 | ||||
| PTMISEA-99313 |
$925 | $0 | $925 | ||||
| PTMISEA-99314 |
$90 | $0 | $90 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$1,100 | $0 | $1,100 | ||||
| Local** |
$1,035 | $0 | $1,035 | ||||
| Total**** | $3,150 | $9 | $3,159 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$20 | $0 | $20 | $0 | $0 | $20 | |
| Design(PS&E) |
$130 | $9 | $139 | $4 | $4 | $135 | |
| Right of Way |
$1,500 | $0 | $1,500 | $1,098 | $1,098 | $402 | |
| Construction |
$1,500 | $0 | $1,500 | $2,057 | $2,057 | $-557 | |
| Total* | $3,150 | $9 | $3,159 | $3,159 | $3,159 | $-0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
03/01/2008 06/30/2008 |
|
03/01/2008 06/30/2008 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/01/2008 06/30/2008 |
|
03/01/2008 06/30/2008 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
03/01/2008 03/31/2009 |
|
03/01/2008 03/31/2009 |
100 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
07/01/2009 06/30/2010 |
05/20/2010 09/13/2011 |
10/01/2009 07/31/2011 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
10/01/2010 12/01/2010 |
09/13/2011 09/13/2011 |
08/01/2011 08/01/2011 |
0 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase in Ridership (percent) | 50 | |
| Useful Life (years) | 50 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$1,015,390 |
| Current Approved: |
$1,015,390 |
| Actual Expenditures: |
$1,015,390 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31
