| Coordinated Paratransit Manag. Sys. | 
| Description: Coordination of paratransit services | 
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County | Ventura | 
| City | Ventura | 
| Zip Code | 93003 | 
| Senate District | 17, 19, 23 | 
| Assembly District | 35, 37, 38, 41 | 
| Congressional District | |
| Caltrans District | 07 | 
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increase in Ridership (percent) | 10 | |
| Increased Ridership | 8 | |
| Useful Life (years) | 5 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA | Ventura County Transportation Commission | Steve DeGeorge | (805) 642-1591 X103 | sdegeorge@goventura.org | 
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a | Approved Changes (06/30/2025 b=c-a | Current Approved (06/30/2025 c | |||||
| Bond Funding | |||||||
| PTMISEA-99313 | $1,400 | $-232 | $1,168 | ||||
| Non-bond Funding | |||||||
| State/Federal* | $1,395 | $-227 | $1,168 | ||||
| Total**** | $2,795 | $-460 | $2,335 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a | Approved Changes (06/30/2025 b=c-a | Current Approved (06/30/2025 c | Cost to Date** (06/30/2025 d | Cost Forecast (06/30/2025 e | Cost Variance f=c-e | ||
| Environmental | $0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) | $0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way | $0 | $0 | $0 | $0 | $0 | $0 | |
| Construction | $2,795 | $-460 | $2,335 | $1,168 | $1,168 | $1,168 | |
| Total* | $2,795 | $-460 | $2,335 | $1,168 | $1,168 | $1,168 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a | Approved Changes (mm/dd/yyyy) b | Current Approved (06/30/2025) c | % Complete (06/30/2025) d | Schedule Forecast (06/30/2025) e | Schedule Variance (months) f=c-e | 
| Begin Environmental Phase End Environmental Phase | 09/13/2007 09/13/2007 |  | 09/13/2007 09/13/2007 | 100 |  | 0 0 | 
| Begin Design (PS&E) Phase End Design (PS&E) Phase |  |  |  | 0 |  | 0 0 | 
| Begin Right of Way Phase End Right of Way Phase |  |  |  | 0 |  | 0 0 | 
| Begin Construction Phase End Construction Phase | 09/17/2007 09/30/2008 |  | 09/17/2007 09/30/2008 | 95 |  | 0 0 | 
| Begin Closeout Phase End Closeout Phase | 10/15/2008 04/30/2009 |  | 10/15/2008 04/30/2009 | 0 |  | 0 0 | 
                                ????????
                            
                            
                            
                        No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increase in Ridership (percent) | 10 | |
| Increased Ridership | 8 | |
| Useful Life (years) | 5 | |
| Bond Funding Cost | |
|---|---|
| Adopted: | $1,400,000 | 
| Current Approved: | $1,167,727 | 
| Actual Expenditures: | $1,167,727 | 
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31