Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Sutter Hill Transit Center |
|
Description: Construct 6-bay transfer facility
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Amador |
| City | Jackson |
| Zip Code | 95642 |
| Senate District |
01 |
| Assembly District | 10 |
| Congressional District | 03 |
| Caltrans District |
10 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 50 | |
| Increase System Reliability (percent) | 10 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
amador County Transportation Commission | Charles Field | (209) 267-2282 | charles@actc-amador.org |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $18 | $18 | ||||
| PTMISEA-99313 |
$307 | $0 | $307 | ||||
| PTMISEA-99314 |
$24 | $0 | $24 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$1,121 | $-64 | $1,057 | ||||
| Local** |
$600 | $-479 | $121 | ||||
| Total**** | $2,052 | $-525 | $1,527 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$200 | $-200 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$400 | $-400 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$1,452 | $75 | $1,527 | $1,527 | $1,527 | $0 | |
| Total* | $2,052 | $-525 | $1,527 | $1,527 | $1,527 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
10/07/2009 03/30/2010 |
11/01/2008 08/15/2009 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
07/01/2008 06/30/2009 |
03/09/2011 03/09/2011 |
04/30/2011 06/30/2012 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
06/30/2009 09/30/2009 |
08/25/2011 08/14/2012 |
06/30/2012 08/15/2012 |
0 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 50 | |
| Increase System Reliability (percent) | 10 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$331,287 |
| Current Approved: |
$331,287 |
| Actual Expenditures: |
$331,287 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31
