Colusa Transit Bus Covered Parking with Solar Panel Roofing |
|
Description: Install covered parking shelters for buses with solar PV system on roof.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Colusa |
| City | Colusa |
| Zip Code | 95932 |
| Senate District |
04 |
| Assembly District | 03 |
| Congressional District | 03 |
| Caltrans District |
03 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 5 | |
| Increased Ridership | 5 | |
| Reduced Emissions | 10 | |
| Reduced Operating/Maintenance Cost | 25 | 10 |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
MIKE AZEVEDO | (530) 458-0471 | MJAZEVEDO@COUNTYOFCOLUSA.ORG |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99313 |
$344 | $143 | $487 | ||||
| PTMISEA-99314 |
$22 | $56 | $78 | ||||
| Non-bond Funding | |||||||
| Total**** | $366 | $200 | $566 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$14 | $0 | $14 | $13 | $13 | $1 | |
| Right of Way |
$0 | $0 | $0 | $1 | $1 | $-1 | |
| Construction |
$352 | $200 | $552 | $552 | $552 | $-0 | |
| Total* | $366 | $200 | $566 | $566 | $566 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
02/01/2014 02/25/2014 |
|
02/01/2014 02/25/2014 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/01/2014 04/01/2014 |
09/16/2017 09/16/2017 |
10/01/2017 04/17/2018 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
06/01/2014 08/01/2014 |
09/25/2019 08/26/2021 |
09/01/2018 05/01/2023 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
09/01/2014 10/01/2014 |
02/02/2023 02/02/2023 |
05/01/2023 05/31/2023 |
0 | |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 5 | |
| Increased Ridership | 5 | |
| Reduced Emissions | 10 | |
| Reduced Operating/Maintenance Cost | 25 | 10 |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$366,000 |
| Current Approved: |
$565,612 |
| Actual Expenditures: |
$565,612 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31