GGBHTD Build Data Center |
|
Description: Project will construct a modern data center to improve communications resulting in a more safe, secure and effective service.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Marin |
| City | San Francisco |
| Zip Code | 94129 |
| Senate District |
03, 08 |
| Assembly District | 06, 12, 13 |
| Congressional District | |
| Caltrans District |
04 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Percent of existing system Modernized | 100 | |
| Reduced Operating/Maintenance Cost | ||
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
Golden Gate Bridge, Hwy & Transportation District | Gayle S. Prior | (414) 923-2373 | gprior@goldengate.org |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99314 |
$1,600 | $0 | $1,600 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$0 | $744 | $744 | ||||
| Local** |
$0 | $172 | $172 | ||||
| Total**** | $1,600 | $916 | $2,516 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$200 | $0 | $200 | $0 | $0 | $200 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$1,400 | $916 | $2,316 | $2,516 | $2,516 | $-200 | |
| Total* | $1,600 | $916 | $2,516 | $2,516 | $2,516 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/01/2008 04/01/2008 |
08/12/2010 08/12/2010 |
01/13/2009 02/10/2009 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
08/01/2008 08/01/2009 |
03/21/2011 03/21/2011 |
04/23/2009 04/30/2011 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
09/01/2010 10/01/2010 |
03/21/2011 10/07/2011 |
11/01/2011 01/31/2012 |
100 | |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Percent of existing system Modernized | 100 | |
| Reduced Operating/Maintenance Cost | ||
| Bond Funding Cost | |
|---|---|
| Adopted: |
$1,600,000 |
| Current Approved: |
$1,600,000 |
| Actual Expenditures: |
$1,600,000 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31