SFMTA Wayside Fare Collection Equipment |
|
Description: Project will replace obsolete fare collection system at subway stations and surface stops to include the implementation of TransLink.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
San Francisco |
| City | San Francisco |
| Zip Code | 94103 |
| Senate District |
03, 08 |
| Assembly District | 12, 13 |
| Congressional District | |
| Caltrans District |
04 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase in Ridership (percent) | ||
| Reduced Operating/Maintenance Cost | 10 | |
| Useful Life (years) | 20 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
San Francisco Municipal Transportation Agency | Joel Goldberg | (415) 701-4499 | joel.goldberg@sfmta.com |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99314 |
$1,000 | $0 | $1,000 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$28,200 | $-9,961 | $18,239 | ||||
| Local** |
$6,177 | $-2,735 | $3,442 | ||||
| Total**** | $35,377 | $-12,697 | $22,680 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$1,648 | $-1,648 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$5,000 | $-5,000 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$28,729 | $-6,049 | $22,680 | $22,680 | $22,680 | $0 | |
| Total* | $35,377 | $-12,697 | $22,680 | $22,680 | $22,680 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2008 12/01/2009 |
09/19/2014 |
01/01/2008 12/01/2009 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
01/01/2010 12/01/2011 |
09/19/2014 08/16/2010 |
11/01/2009 08/31/2010 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
01/01/2012 07/01/2012 |
09/19/2014 09/19/2014 |
10/31/2012 08/31/2014 |
100 | |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase in Ridership (percent) | ||
| Reduced Operating/Maintenance Cost | 10 | |
| Useful Life (years) | 20 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$1,000,000 |
| Current Approved: |
$1,000,000 |
| Actual Expenditures: |
$1,000,000 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31