                            BART Ashby Elevator | 
                    
| 
                            Description: Project is to construct a new elevator at Ashby Station to accomodate the Ed Roberts campus
                             | 
                    
- Project Information
 - Contacts
 - Cost by Fund Source
 - Cost by Component
 - Schedule
 - Map
 - Closeout Info
 
| Project Location | |
|---|---|
| County | 
                                    Alameda | 
| City | Oakland | 
| Zip Code | 94604 | 
| Senate District | 
                                    03, 09 | 
                                
| Assembly District | 13, 16 | 
| Congressional District | |
| Caltrans District | 
                                    04 | 
                                
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increase in Ridership (percent) | ||
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA | 
                                    
                                    
                                        
                                            San Francisco Bay Area Rapid Transit District | Kenneth A. Duron | (510) 464-6083 | boardofdirectors@bart.gov | 
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a  | 
                                    Approved Changes (06/30/2025 b=c-a  | 
                                    Current Approved (06/30/2025 c  | 
                                |||||
| Bond Funding | |||||||
| PTMISEA-99313 | 
                                            $2,000 | $-271 | $1,729 | ||||
| Non-bond Funding | |||||||
| State/Federal* | 
                                            $4,000 | $-2,297 | $1,703 | ||||
| Local** | 
                                            $1,000 | $-20 | $980 | ||||
| Total**** | $7,000 | $-2,588 | $4,412 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a  | 
                                    Approved Changes (06/30/2025 b=c-a  | 
                                    Current Approved (06/30/2025 c  | 
                                    Cost to Date** (06/30/2025 d  | 
                                    
                                        
                                            Cost Forecast (06/30/2025 e  | 
                                            Cost Variance f=c-e  | 
                                        
                                    
                                ||
| Environmental | 
                                        $0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) | 
                                        $500 | $285 | $785 | $785 | $785 | $0 | |
| Right of Way | 
                                    $0 | $0 | $0 | $0 | $0 | $0 | |
| Construction | 
                                    $6,500 | $-2,873 | $3,627 | $3,627 | $3,627 | $0 | |
| Total* | $7,000 | $-2,588 | $4,412 | $4,412 | $4,412 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a  | 
                                    Approved Changes (mm/dd/yyyy) b  | 
                                    Current Approved (06/30/2025) c  | 
                                    % Complete (06/30/2025) d  | 
                                    Schedule Forecast (06/30/2025) e  | 
                                    Schedule Variance (months) f=c-e  | 
                                
| 
                                        
                                            Begin Environmental Phase
                                             End Environmental Phase  | 
                                      | 
                                      | 
                                      | 
                                    100 |   | 
                                    0  0  | 
                                
| 
                                        Begin Design (PS&E) Phase
                                         End Design (PS&E) Phase  | 
                                    11/01/2007  04/01/2008  | 
                                      01/02/2013  | 
                                    11/01/2007  09/23/2008  | 
                                    100 |   | 
                                    0  0  | 
                                
| 
                                        Begin Right of Way Phase
                                         End Right of Way Phase  | 
                                      | 
                                      | 
                                      | 
                                    0 |   | 
                                    0  0  | 
                                
| 
                                        Begin Construction Phase
                                         End Construction Phase  | 
                                    08/01/2008  04/01/2010  | 
                                    08/13/2010  01/02/2013  | 
                                    03/16/2009  11/23/2011  | 
                                    100 |   | 
                                    0  0  | 
                                
| 
                                        Begin Closeout Phase
                                         End Closeout Phase  | 
                                    12/01/2010  06/01/2011  | 
                                    03/06/2012  01/02/2013  | 
                                    12/02/2011  11/30/2012  | 
                                    0 |   | 
                                    0  0  | 
                                
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increase in Ridership (percent) | ||
| Bond Funding Cost | |
|---|---|
| Adopted: | 
                                    $2,000,000 | 
| Current Approved: | 
                                    $1,729,046 | 
| Actual Expenditures: | 
                                    $1,729,046 | 
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31