MacArthur Transit Village Plaza Improvements |
|
Description: Renovation of the enrty plaza at the MacArthur BART Station
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Alameda |
| City | Oakland |
| Zip Code | 94612 |
| Senate District |
13, 16 |
| Assembly District | 03, 09 |
| Congressional District | 07, 08, 09, 10, 11, 13 |
| Caltrans District |
04 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 2 | 1 |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
DONNA LEE | (510) 464-6282 | DLEE@BART.GOV |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$29 | $9 | $37 | ||||
| PTMISEA-99313 |
$271 | $62 | $333 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$2,069 | $889 | $2,958 | ||||
| Local** |
$259 | $5,169 | $5,428 | ||||
| Total**** | $2,628 | $6,128 | $8,756 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$100 | $-100 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$259 | $-259 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$2,269 | $6,487 | $8,756 | $8,756 | $8,756 | $0 | |
| Total* | $2,628 | $6,128 | $8,756 | $8,756 | $8,756 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/2007 08/31/2009 |
|
07/01/2007 08/31/2009 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/01/2010 12/31/2012 |
|
02/01/2010 12/31/2012 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
02/01/2012 05/31/2013 |
03/04/2020 |
02/01/2012 04/30/2019 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
06/01/2013 12/31/2013 |
03/04/2020 03/04/2020 |
04/30/2019 12/31/2019 |
0 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 2 | 1 |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$299,724 |
| Current Approved: |
$332,534 |
| Actual Expenditures: |
$332,534 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31