City of Vallejo Replace 9 Buses |
|
Description: Project will replace nine (9) 40-foot depreciated transit buses with eight (8) hybrid/diesel and one (1) diesel buses
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Solano |
| City | Vallejo |
| Zip Code | 94590 |
| Senate District |
02 |
| Assembly District | 11 |
| Congressional District | |
| Caltrans District |
04 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Decreased Maintenance Cost (percent) | ||
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
City of Vallejo | Crystal Odum Ford | (707) 648-5241 | codumford@ci.vallejo.ca.us |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99314 |
$589 | $0 | $589 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$8,127 | $-3,051 | $5,076 | ||||
| Local** |
$0 | $185 | $185 | ||||
| Total**** | $8,716 | $-2,866 | $5,849 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$8,716 | $-2,866 | $5,849 | $5,849 | $5,849 | $0 | |
| Total* | $8,716 | $-2,866 | $5,849 | $5,849 | $5,849 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
07/01/2008 12/01/2009 |
06/29/2012 06/29/2012 |
10/27/2009 04/30/2011 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
|
03/29/2011 03/29/2011 |
05/30/2011 06/30/2011 |
0 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Decreased Maintenance Cost (percent) | ||
| Bond Funding Cost | |
|---|---|
| Adopted: |
$588,641 |
| Current Approved: |
$588,641 |
| Actual Expenditures: |
$588,641 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31