Description: Construct transit center
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Santa Barbara |
| City | Lompoc |
| Zip Code | 93438 |
| Senate District |
19 |
| Assembly District | 33 |
| Congressional District | |
| Caltrans District |
05 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 20 | |
| Increase System Reliability (percent) | 10 | |
| Increase in Ridership (percent) | 10 | |
| Increased Ridership | 10 | |
| Reduced Emissions | 5 | |
| Reduced Operating/Maintenance Cost | 5 | |
| Useful Life (years) | 30 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
City of Lompoc Transit/Colt | Richard L. Fernbaugh | (805) 875-8268 | rfernbaugh@ci.lompoc.ca.us |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $19 | $19 | ||||
| PTMISEA-99313 |
$1,972 | $-1,194 | $778 | ||||
| PTMISEA-99314 |
$57 | $-35 | $22 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$100 | $-100 | $0 | ||||
| Local** |
$0 | $249 | $249 | ||||
| Total**** | $2,130 | $-1,062 | $1,068 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$100 | $-100 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$0 | $50 | $50 | $64 | $64 | $-14 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$2,030 | $-1,012 | $1,018 | $1,004 | $1,004 | $14 | |
| Total* | $2,130 | $-1,062 | $1,068 | $1,068 | $1,068 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
06/01/2008 05/31/2009 |
03/29/2017 |
06/01/2008 12/30/2015 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2009 05/31/2010 |
03/29/2017 03/29/2017 |
01/30/2016 06/30/2017 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
10/01/2009 05/31/2010 |
03/29/2017 03/29/2017 |
06/01/2017 06/30/2017 |
100 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
06/15/2010 03/31/2011 |
05/04/2018 05/04/2018 |
10/01/2017 03/31/2018 |
90 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
04/01/2011 06/30/2011 |
05/04/2018 05/04/2018 |
04/01/2018 04/30/2018 |
100 | |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 20 | |
| Increase System Reliability (percent) | 10 | |
| Increase in Ridership (percent) | 10 | |
| Increased Ridership | 10 | |
| Reduced Emissions | 5 | |
| Reduced Operating/Maintenance Cost | 5 | |
| Useful Life (years) | 30 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$2,029,787 |
| Current Approved: |
$800,000 |
| Actual Expenditures: |
$800,000 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31