San Gabriel Valley Park&Ride |
|
Description: Construction of a four-level parking structure with 511 parking spaces.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Los Angeles |
| City | West Covina |
| Zip Code | 91790 |
| Senate District |
30 |
| Assembly District | 59 |
| Congressional District | |
| Caltrans District |
07 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 5 | 100 |
| Reduced Emissions | 90 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
RUBEN CERVANTES | (626) 931-7231 | RCERVANTES@FOOTHILLTRANSIT.ORG |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $51 | $51 | ||||
| PTMISEA-99314 |
$3,271 | $0 | $3,271 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$14,574 | $50,414 | $64,988 | ||||
| Local** |
$0 | $5,793 | $5,793 | ||||
| Total**** | $17,846 | $56,258 | $74,103 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$600 | $700 | $1,300 | $0 | $0 | $1,300 | |
| Design(PS&E) |
$1,200 | $300 | $1,500 | $121 | $121 | $1,379 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$16,046 | $55,258 | $71,303 | $3,201 | $3,201 | $68,102 | |
| Total* | $17,846 | $56,258 | $74,103 | $3,322 | $3,322 | $70,781 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/2011 04/01/2012 |
09/20/2010 09/20/2010 |
07/01/2011 04/01/2012 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/01/2012 01/01/2013 |
09/20/2010 03/07/2013 |
05/01/2012 10/01/2012 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
02/01/2013 08/01/2014 |
03/07/2013 09/27/2013 |
10/01/2012 12/01/2015 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
09/01/2014 11/01/2014 |
05/09/2017 05/09/2017 |
06/01/2016 03/01/2017 |
100 | |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 5 | 100 |
| Reduced Emissions | 90 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$3,271,166 |
| Current Approved: |
$3,271,166 |
| Actual Expenditures: |
$3,271,166 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31