Yuba Sutter Transit Operations, Maint., Admin., Facility Expansion |
|
Description: To provide for the design engineering, construction, furnishing and equipping to expand the existing facility and property.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Sacramento, Yuba |
| City | Sacramento |
| Zip Code | 95814 |
| Senate District |
05, 06 |
| Assembly District | 09 |
| Congressional District | 05 |
| Caltrans District |
03 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 200 | |
| Increased Ridership | 6 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
Sacamento Area Council of Governments | Gary Taylor | (916) 340-6279 | gtaylor@sacog.org |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $300 | $300 | ||||
| PTMISEA-99313 |
$2,062 | $260 | $2,322 | ||||
| PTMISEA-99314 |
$45 | $0 | $45 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$0 | $604 | $604 | ||||
| Total**** | $2,106 | $1,164 | $3,270 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$160 | $384 | $544 | $541 | $541 | $3 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$1,946 | $780 | $2,726 | $2,726 | $2,726 | $0 | |
| Total* | $2,106 | $1,164 | $3,270 | $3,267 | $3,267 | $3 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2009 03/31/2009 |
|
01/01/2009 03/31/2009 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
07/01/2009 06/30/2010 |
02/25/2011 |
07/01/2009 11/30/2011 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
07/01/2010 07/31/2010 |
08/17/2012 08/17/2012 |
03/30/2012 09/30/2012 |
100 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 200 | |
| Increased Ridership | 6 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$2,106,448 |
| Current Approved: |
$2,366,448 |
| Actual Expenditures: |
$2,366,448 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31