City of Fresno/FAX/Paratransit Facility |
|
Description: Fresno Area Express (FAX) is proposing to purchase property that includes the space and structures needed to appropriately house its paratransit equipment and operations.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Fresno |
| City | Fresno |
| Zip Code | 93706 |
| Senate District |
14, 16 |
| Assembly District | 31 |
| Congressional District | 20 |
| Caltrans District |
06 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 5 | 3 |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
Darlene Christiansen | (559) 621-1469 | Darlene.Christiansen@FRESNO.GOV |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99313 |
$2,143 | $200 | $2,343 | ||||
| PTMISEA-99314 |
$1,057 | $-255 | $802 | ||||
| Non-bond Funding | |||||||
| Total**** | $3,200 | $-55 | $3,145 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$200 | $-200 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$3,000 | $145 | $3,145 | $3,145 | $3,145 | $0 | |
| Total* | $3,200 | $-55 | $3,145 | $3,145 | $3,145 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
05/01/2009 06/30/2009 |
02/15/2011 02/15/2011 |
07/01/2010 12/31/2010 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/01/2009 09/30/2009 |
09/13/2011 09/29/2015 |
11/01/2010 07/31/2016 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
10/01/2009 09/30/2010 |
09/13/2011 09/29/2015 |
05/01/2011 11/30/2016 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
09/01/2010 11/30/2010 |
08/12/2019 08/12/2019 |
12/31/2017 02/01/2018 |
100 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 5 | 3 |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$3,199,912 |
| Current Approved: |
$3,145,017 |
| Actual Expenditures: |
$3,145,017 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31