Description: Purchase 6 replacement diesel buses
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Kern |
| City | Bakersfield |
| Zip Code | 93301 |
| Senate District |
18 |
| Assembly District | 32 |
| Congressional District | 20, 22 |
| Caltrans District |
06 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Reduced Operating/Maintenance Cost | 5 | 5 |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
BETTY DENNISON | (661) 862-8616 | DENNISONB@CO.KERN.CA.US |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99313 |
$313 | $-204 | $109 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$496 | $0 | $496 | ||||
| Total**** | $809 | $-204 | $605 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$809 | $-204 | $605 | $605 | $605 | $0 | |
| Total* | $809 | $-204 | $605 | $605 | $605 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
10/13/2009 12/31/2009 |
08/26/2011 08/26/2011 |
10/13/2009 03/31/2010 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
01/31/2010 10/15/2010 |
08/26/2011 08/26/2011 |
03/15/2011 07/31/2011 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
12/15/2010 01/30/2012 |
05/06/2014 05/06/2014 |
02/15/2012 08/15/2012 |
100 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Reduced Operating/Maintenance Cost | 5 | 5 |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$312,622 |
| Current Approved: |
$108,932 |
| Actual Expenditures: |
$108,932 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31