Citywide Bus Bench Installations

Description: Citywide Bus Bench Installations for the City of National City

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City National City
Zip Code 91950
 
Senate District
40
Assembly District 79
Congressional District 51
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
STEPHEN MANGANIELLO (619) 336-4382   SMANGANIELLO@NATIONALCITYCA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99314
$129 $0 $129
Non-bond Funding
 
Total**** $129 $1 $130

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$129 $1 $130 $130 $130 $0
 
Total* $129 $1 $130 $130 $130 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/01/2010 

04/01/2010 
 

 
03/01/2010 

04/01/2010 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2010 

05/01/2010 
 

 
05/01/2010 

05/01/2010 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2010 

12/01/2010 
08/17/2012 

08/17/2012 
03/19/2012 

07/18/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2010 

01/05/2011 
08/17/2012 

08/17/2012 
07/28/2012 

09/04/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 10

Bond Funding Cost
Adopted:
$129,147
Current Approved:
$130,225
Actual Expenditures:
$130,225

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31