Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Purchase of 20 CNG Transit Buses |
|
Description: Purchase of 20 replacement CNG buses
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Los Angeles |
| City | Culver City |
| Zip Code | 90232 |
| Senate District |
26 |
| Assembly District | 47 |
| Congressional District | |
| Caltrans District |
07 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 15 | 15 |
| Reduced Emissions | 95 | 95 |
| Reduced Operating/Maintenance Cost | 15 | 15 |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
JANE LEONARD | (310) 253-6523 | JANE.LEONARD@CULVERCITY.ORG |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99314 |
$933 | $374 | $1,307 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$8,800 | $-800 | $8,000 | ||||
| Local** |
$788 | $-94 | $693 | ||||
| Total**** | $10,521 | $-521 | $10,000 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$10,521 | $-521 | $10,000 | $1,307 | $1,307 | $8,693 | |
| Total* | $10,521 | $-521 | $10,000 | $1,307 | $1,307 | $8,693 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
09/01/2010 10/01/2011 |
03/08/2012 03/08/2012 |
08/01/2011 04/01/2012 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
10/01/2011 11/01/2011 |
09/05/2012 09/05/2012 |
09/01/2012 09/30/2012 |
0 | |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 15 | 15 |
| Reduced Emissions | 95 | 95 |
| Reduced Operating/Maintenance Cost | 15 | 15 |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$932,957 |
| Current Approved: |
$1,306,824 |
| Actual Expenditures: |
$1,306,824 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31
