Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Plumas County Bus Yard |
|
Description: Construction of a bus parking area within the Plumas County Maintenance Yard in Quincy
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Plumas |
| City | Quincy |
| Zip Code | 95971 |
| Senate District |
03 |
| Assembly District | 01 |
| Congressional District | 04 |
| Caltrans District |
02 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 100 | 33 |
| Reduced Operating/Maintenance Cost | 10 | 5 |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
JOHN MANNLE | (530) 283-6498 | JOHNMANNLE@COUNTYOFPLUMAS.COM |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| LSR |
$0 | $86 | $86 | ||||
| PTMISEA-Interest |
$0 | $42 | $42 | ||||
| PTMISEA-99313 |
$319 | $92 | $411 | ||||
| Non-bond Funding | |||||||
| Local** |
$0 | $8 | $8 | ||||
| Total**** | $319 | $228 | $547 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $8 | $8 | $8 | $8 | $0 | |
| Design(PS&E) |
$75 | $-75 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$244 | $294 | $538 | $538 | $538 | $0 | |
| Total* | $319 | $228 | $547 | $547 | $547 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
09/12/2012 09/12/2012 |
11/01/2011 08/01/2012 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/01/2012 05/01/2013 |
10/19/2011 09/21/2016 |
09/01/2012 04/06/2016 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
06/01/2013 10/01/2013 |
09/21/2016 09/05/2023 |
04/07/2016 06/30/2023 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
11/01/2013 01/01/2014 |
09/05/2023 02/15/2023 |
06/01/2023 06/30/2023 |
0 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 100 | 33 |
| Reduced Operating/Maintenance Cost | 10 | 5 |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$318,930 |
| Current Approved: |
$410,660 |
| Actual Expenditures: |
$410,660 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31
