LA 5 Truck Climbing Lanes

Description: In Santa Clarita from Route 14 to Pico Canyon/Lyons Avenue in the southbound direction and from Route 14 to Gavin Canyon Road in the northbound direction. Const truck climbing lanes.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Santa Clarita
Zip Code 91321
 
Senate District
17, 19
Assembly District 38
Congressional District 25
 
Caltrans District
07
 
 
County/State Route Los Angeles 5
Postmile Begin/End 46.3 50
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  2.74      
Lane Miles Added (HOV)      5.1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation John K. Lee (213) 897-8623   john.k.lee@dot.ca.gov
Design (PS&E) Phase
Department of Transportation John K. Lee (213) 897-8623   john.k.lee@dot.ca.gov
Right of Way Phase
Department of Transportation John K. Lee (213) 897-8623   john.k.lee@dot.ca.gov
Construction Phase
Department of Transportation John K. Lee (213) 897-8623   john.k.lee@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$75,000 $-69,038 $5,962
Non-bond Funding
State/Federal*
$0 $75,000 $75,000
Local**
$0 $0 $0
 
Total**** $75,000 $5,962 $80,962

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $0 $0 $0
Design(PS&E)
$12,308 $5,962 $18,270 $5,962
Right of Way
$110 $0 $110 $115
Construction
$62,582 $0 $62,582 $62,123
 
Total* $75,000 $5,962 $80,962 $68,200

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
05/02/2007 

09/29/2009 
100  05/02/2007 

09/29/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

01/27/2011 
100   

01/27/2011 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
12/02/2009 

 
100  12/02/2009 

 


Begin Construction Phase

End Construction Phase
03/22/2012 

12/31/2014 
 

 
03/15/2012 

04/21/2015 
100  03/15/2012 

04/21/2015 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

07/14/2017 
 

07/24/2019 


-25 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 2.74
Lane Miles Added (HOV) 5.1

Bond Funding Cost
Adopted:
$75,000,000
Current Approved:
$5,962,000
Actual Expenditures:
$5,962,000

 

Status as of December 31, 2023.