Caltrans Logo

Roadway Rehabilitation and Upgrade Median Barrier

Description: In Los Angeles, from Imperial Highway to Firestone Boulevard. Rehabilitate roadway. (Prop 1B Bond Funded Project)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Lynwood, South Gate
Zip Code 90262, 90280
 
Senate District
27
Assembly District 50
Congressional District 39
 
Caltrans District
07
 
 
County/State Route Los Angeles 710
Postmile Begin/End 16.1 18.4
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      N/A  
Distress Pavement Lane Miles Retired  12      
Pavement Lane Miles  13      
Peak Period Time Savings (minutes)      N/A  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation John Vassiliades (213) 897-7395   John_Vassiliades@dot.ca.gov
Design (PS&E) Phase
Department of Transportation John Vassiliades (213) 897-7395   John_Vassiliades@dot.ca.gov
Right of Way Phase
Department of Transportation John Vassiliades (213) 897-7395   John_Vassiliades@dot.ca.gov
Construction Phase
Department of Transportation Sharas Bangalore (213) 897-8905   Sharas_bangalore@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Sharas Bangalore (213) 897-8905   sharas_bangalore@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$51,000 $0 $51,000
Non-bond Funding
Non Budgeted ETC
$0 $0 $0
 
Total**** $51,000 $0 $51,000

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $0 $0 $0
Design(PS&E)
$4,000 $0 $4,000 $2,272
Right of Way
$100 $0 $100 $0
Construction
$46,900 $0 $46,900 $40,421
 
Total* $51,000 $0 $51,000 $42,693

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/1996 

10/01/1997 
 

 
01/01/1996 

10/01/1997 
100  01/01/1996 

09/18/2007 


-121 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2007 

04/01/2008 
 

 
07/01/2007 

04/01/2008 
100  07/01/2007 

05/21/2008 


-2 
Begin Right of Way Phase

End Right of Way Phase
07/01/2007 

03/01/2008 
 

 
07/01/2007 

03/01/2008 
100  07/21/2007 

02/29/2008 
-1 

Begin Construction Phase

End Construction Phase
10/01/2008 

11/01/2010 
 

 
10/01/2008 

11/01/2010 
100  10/01/2008 

07/21/2011 


-9 
Begin Closeout Phase

End Closeout Phase
12/01/2010 

12/01/2011 
 

 
12/01/2010 

12/01/2011 
100  02/02/2012 

02/06/2014 
-14 

-27 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) N/A
Distress Pavement Lane Miles Retired 12
Pavement Lane Miles 13
Peak Period Time Savings (minutes) N/A

Bond Funding Cost
Adopted:
$51,000,000
Current Approved:
$47,270,000
Actual Expenditures:
$42,692,796

Click to view the Final Audit Report

 

Status as of December 31, 2023.