Bond Accountability
Roadway Rehabilitation and Upgrade Median Barrier |
Description: In Los Angeles, from Imperial Highway to Firestone Boulevard. Rehabilitate roadway. (Prop 1B Bond Funded Project)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Lynwood, South Gate |
Zip Code | 90262, 90280 |
Senate District |
27 |
Assembly District | 50 |
Congressional District | 39 |
Caltrans District |
07 |
County/State Route | Los Angeles 710 |
Postmile Begin/End | 16.1 18.4 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | N/A | |
Distress Pavement Lane Miles Retired | 12 | |
Pavement Lane Miles | 13 | |
Peak Period Time Savings (minutes) | N/A |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | John Vassiliades | (213) 897-7395 | John_Vassiliades@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | John Vassiliades | (213) 897-7395 | John_Vassiliades@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | John Vassiliades | (213) 897-7395 | John_Vassiliades@dot.ca.gov | |
Construction Phase |
Department of Transportation | Sharas Bangalore | (213) 897-8905 | Sharas_bangalore@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Sharas Bangalore | (213) 897-8905 | sharas_bangalore@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$51,000 | $0 | $51,000 | ||||
Non-bond Funding | |||||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $51,000 | $0 | $51,000 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$0 | $0 | $0 | $0 | |||
Design(PS&E) |
$4,000 | $0 | $4,000 | $2,272 | |||
Right of Way |
$100 | $0 | $100 | $0 | |||
Construction |
$46,900 | $0 | $46,900 | $40,421 | |||
Total* | $51,000 | $0 | $51,000 | $42,693 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/1996 10/01/1997 |
|
01/01/1996 10/01/1997 |
100 | 01/01/1996 09/18/2007 |
0 -121 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2007 04/01/2008 |
|
07/01/2007 04/01/2008 |
100 | 07/01/2007 05/21/2008 |
0 -2 |
Begin Right of Way Phase
End Right of Way Phase |
07/01/2007 03/01/2008 |
|
07/01/2007 03/01/2008 |
100 | 07/21/2007 02/29/2008 |
-1 0 |
Begin Construction Phase
End Construction Phase |
10/01/2008 11/01/2010 |
|
10/01/2008 11/01/2010 |
100 | 10/01/2008 07/21/2011 |
0 -9 |
Begin Closeout Phase
End Closeout Phase |
12/01/2010 12/01/2011 |
|
12/01/2010 12/01/2011 |
100 | 02/02/2012 02/06/2014 |
-14 -27 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | N/A | |
Distress Pavement Lane Miles Retired | 12 | |
Pavement Lane Miles | 13 | |
Peak Period Time Savings (minutes) | N/A |
Bond Funding Cost | |
---|---|
Adopted: |
$51,000,000 |
Current Approved: |
$47,270,000 |
Actual Expenditures: |
$42,692,796 |
Status as of December 31, 2023.