LA-710 Long Life Pavement Rehabilitation

Description: In Los Angeles, from 0.3 mile south of Firestone Boulevard to 0.2 mile south of Slauson Avenue. Rehabilitate roadway. (Prop 1B Bond Funded Project)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Bell, Bell Gardens, Commerce, South Gate
Zip Code 90040, 90201, 90280
 
Senate District
27, 30
Assembly District 50
Congressional District 34, 39
 
Caltrans District
07
 
 
County/State Route Los Angeles 710
Postmile Begin/End 18.1 20.8
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)  22      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Gabe Hamidi (213) 897-5354   Gabe_hamidi@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Gabe Hamidi (213) 897-5354   Gabe_hamidi@dot.ca.gov
Right of Way Phase
Department of Transportation Gabe Hamidi (213) 897-5354   Gabe_hamidi@dot.ca.gov
Construction Phase
Department of Transportation Gabe Hamidi (213) 897-5354   Gabe_hamidi@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Gabe Hamidi (213) 897-5354   Gabe_hamidi@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$83,850 $-79,772 $4,078
Non-bond Funding
State/Federal*
$0 $0 $0
 
Total**** $83,850 $-79,772 $4,078

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $0 $0 $0
Design(PS&E)
$7,000 $4,078 $11,078 $4,078
Right of Way
$1,800 $0 $1,800 $0
Construction
$75,050 $0 $75,050 $53,298
 
Total* $83,850 $-79,772 $4,078 $12,288

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/1999 

09/01/1999 
01/01/1999 

09/01/1999 
01/01/1999 

09/03/1999 
100  01/01/1999 

09/03/1999 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2007 

01/01/2009 
07/01/2007 

 
07/01/2007 

04/24/2009 
100  07/01/2007 

04/24/2009 


Begin Right of Way Phase

End Right of Way Phase
07/01/2008 

05/01/2009 
 

 
05/15/2008 

05/01/2009 
05/15/2008 

05/01/2009 


Begin Construction Phase

End Construction Phase
10/01/2009 

04/01/2014 
 

 
09/22/2009 

04/01/2014 
09/22/2009 

04/01/2014 


Begin Closeout Phase

End Closeout Phase
05/01/2014 

05/01/2015 
 

 
05/01/2014 

05/01/2015 
90  05/01/2014 

05/01/2015 


????????
Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles) 22

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.