Rehabilitate HOV and Bus Lanes

Description: In Los Angeles, from 0.4 mile east of Route 5 to Route 710. Rehabilitate HOV and bus lanes. (Prop 1B Bond Funded Project)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Alhambra
Zip Code 91801
 
Senate District
22, 24
Assembly District 45, 46, 49
Congressional District 29, 32, 34
 
Caltrans District
07
 
 
County/State Route Los Angeles 10
Postmile Begin/End 18.3 21.4
Project Benefits
 Benefit Baseline Actual
Distress Pavement Lane Miles Retired  6      
Pavement Lane Miles  6      
Rehabilitated Lane Miles (miles)      2.95  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Tien Tran (213) 897-1704   tien_tran@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Tien Tran (213) 897-1704   tien_tran@dot.ca.gov
Right of Way Phase
Department of Transportation Tien Tran (213) 897-1704   tien_tran@dot.ca.gov
Construction Phase
Department of Transportation Syed Huq (213) 897-6714   syed_huq@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Tien Tran (213) 897-1704   tien_tran@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$52,000 $0 $52,000
Non-bond Funding
State/Federal*
$0 $0 $0
 
Total**** $52,000 $0 $52,000

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $0 $0 $0
Design(PS&E)
$4,000 $0 $4,000 $891
Right of Way
$100 $0 $100 $0
Construction
$47,900 $0 $47,900 $18,329
 
Total* $52,000 $0 $52,000 $19,220

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/02/2007 

09/12/2007 
 

 
07/02/2007 

09/12/2007 
100  07/02/2007 

09/12/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/15/2007 

03/14/2008 
 

 
09/15/2007 

03/14/2008 
100  09/15/2007 

03/14/2008 


Begin Right of Way Phase

End Right of Way Phase
09/15/2007 

12/06/2008 
 

 
09/15/2007 

12/06/2008 
100  09/15/2007 

12/06/2008 


Begin Construction Phase

End Construction Phase
08/07/2008 

02/25/2010 
 

 
08/07/2008 

02/25/2010 
100  08/07/2008 

02/25/2010 


Begin Closeout Phase

End Closeout Phase
02/26/2010 

05/27/2011 
 

 
02/26/2010 

05/27/2011 
50  02/26/2010 

05/27/2011 


????????
Project Benefits
Benefit Baseline Actual
Distress Pavement Lane Miles Retired 6
Pavement Lane Miles 6
Rehabilitated Lane Miles (miles) 2.95

Bond Funding Cost
Adopted:
$52,000,000
Current Approved:
$52,000,000
Actual Expenditures:
$18,700,000

 

Status as of December 31, 2023.