Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Rehabilitate HOV and Bus Lanes |
Description: In Los Angeles, from 0.4 mile east of Route 5 to Route 710. Rehabilitate HOV and bus lanes. (Prop 1B Bond Funded Project)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Alhambra |
Zip Code | 91801 |
Senate District |
22, 24 |
Assembly District | 45, 46, 49 |
Congressional District | 29, 32, 34 |
Caltrans District |
07 |
County/State Route | Los Angeles 10 |
Postmile Begin/End | 18.3 21.4 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Distress Pavement Lane Miles Retired | 6 | |
Pavement Lane Miles | 6 | |
Rehabilitated Lane Miles (miles) | 2.95 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Tien Tran | (213) 897-1704 | tien_tran@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Tien Tran | (213) 897-1704 | tien_tran@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Tien Tran | (213) 897-1704 | tien_tran@dot.ca.gov | |
Construction Phase |
Department of Transportation | Syed Huq | (213) 897-6714 | syed_huq@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Tien Tran | (213) 897-1704 | tien_tran@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$52,000 | $0 | $52,000 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Total**** | $52,000 | $0 | $52,000 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$0 | $0 | $0 | $0 | |||
Design(PS&E) |
$4,000 | $0 | $4,000 | $891 | |||
Right of Way |
$100 | $0 | $100 | $0 | |||
Construction |
$47,900 | $0 | $47,900 | $18,329 | |||
Total* | $52,000 | $0 | $52,000 | $19,220 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/02/2007 09/12/2007 |
|
07/02/2007 09/12/2007 |
100 | 07/02/2007 09/12/2007 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/15/2007 03/14/2008 |
|
09/15/2007 03/14/2008 |
100 | 09/15/2007 03/14/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
09/15/2007 12/06/2008 |
|
09/15/2007 12/06/2008 |
100 | 09/15/2007 12/06/2008 |
0 0 |
Begin Construction Phase
End Construction Phase |
08/07/2008 02/25/2010 |
|
08/07/2008 02/25/2010 |
100 | 08/07/2008 02/25/2010 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
02/26/2010 05/27/2011 |
|
02/26/2010 05/27/2011 |
50 | 02/26/2010 05/27/2011 |
0 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Distress Pavement Lane Miles Retired | 6 | |
Pavement Lane Miles | 6 | |
Rehabilitated Lane Miles (miles) | 2.95 |
Bond Funding Cost | |
---|---|
Adopted: |
$52,000,000 |
Current Approved: |
$52,000,000 |
Actual Expenditures: |
$18,700,000 |
Status as of December 31, 2023.