Tahoe City Transit Center

Description: Intermodal transit center (6) bus bays and (130) parking spaces

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn
Zip Code 95603
 
Senate District
01
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  25    25  
Useful Life (years)  30      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Placer County Department of Public Works Will Garner (530) 745-7582   wgarner@placer.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$8 $2 $10
PTMISEA-99313
$385 $0 $385
Non-bond Funding
State/Federal*
$4,473 $1,677 $6,151
Local**
$1,897 $-997 $900
 
Total**** $6,763 $683 $7,446

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$296 $0 $296 $0 $0 $296
Design(PS&E)
$733 $135 $867 $1,333 $1,333 $-466
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$5,734 $548 $6,282 $6,112 $6,112 $169
 
Total* $6,763 $683 $7,446 $7,446 $7,446 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2006 

12/01/2008 
 

03/21/2012 
12/01/2006 

04/01/2010 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
05/01/2009 

10/01/2010 
03/21/2012 

03/21/2012 
06/01/2010 

10/01/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2011 

08/01/2011 
03/21/2012 

10/25/2013 
09/01/2012 

04/30/2013 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 25 25
Useful Life (years) 30

Bond Funding Cost
Adopted:
$392,668
Current Approved:
$384,826
Actual Expenditures:
$384,826

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31