Tahoe City Transit Center |
Description: Intermodal transit center (6) bus bays and (130) parking spaces
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Placer |
City | Auburn |
Zip Code | 95603 |
Senate District |
01 |
Assembly District | 04 |
Congressional District | 04 |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 25 | 25 |
Useful Life (years) | 30 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
Placer County Department of Public Works | Will Garner | (530) 745-7582 | wgarner@placer.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$8 | $2 | $10 | ||||
PTMISEA-99313 |
$385 | $0 | $385 | ||||
Non-bond Funding | |||||||
State/Federal* |
$4,473 | $1,677 | $6,151 | ||||
Local** |
$1,897 | $-997 | $900 | ||||
Total**** | $6,763 | $683 | $7,446 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$296 | $0 | $296 | $0 | $0 | $296 | |
Design(PS&E) |
$733 | $135 | $867 | $1,333 | $1,333 | $-466 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$5,734 | $548 | $6,282 | $6,112 | $6,112 | $169 | |
Total* | $6,763 | $683 | $7,446 | $7,446 | $7,446 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/01/2006 12/01/2008 |
03/21/2012 |
12/01/2006 04/01/2010 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/01/2009 10/01/2010 |
03/21/2012 03/21/2012 |
06/01/2010 10/01/2012 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
06/01/2011 08/01/2011 |
03/21/2012 10/25/2013 |
09/01/2012 04/30/2013 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 25 | 25 |
Useful Life (years) | 30 |
Bond Funding Cost | |
---|---|
Adopted: |
$392,668 |
Current Approved: |
$384,826 |
Actual Expenditures: |
$384,826 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31