Mendota Transit Service Expansion

Description: Purchase 4 CNG type buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City
Zip Code
 
Senate District
14, 16
Assembly District 29, 30, 31
Congressional District
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership      100  
Number of New Buses Purchased for Expansion  4      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Fresno County Rural Transit Agency Jeffrey D. Webster 559-233-6789   jwebster_ruraltransit@fresnocog.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$423 $-12 $411
Non-bond Funding
State/Federal*
$1,062 $0 $1,062
 
Total**** $1,485 $-12 $1,474

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,485 $-12 $1,474 $1,474 $1,474 $0
 
Total* $1,485 $-12 $1,474 $1,474 $1,474 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/20/2007 

03/15/2008 
09/29/2008 

10/23/2009 
05/30/2008 

09/30/2008 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2008 

05/01/2008 
09/29/2008 

09/29/2008 
10/30/2008 

11/30/2008 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 100
Number of New Buses Purchased for Expansion 4

Bond Funding Cost
Adopted:
$422,902
Current Approved:
$411,388
Actual Expenditures:
$411,388

Click to view the Semi-Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31