Rolling Stock Replacement Vans

Description: Purchase 7 CNG cut-away vans

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City
Zip Code
 
Senate District
14, 16
Assembly District 29, 30, 31
Congressional District
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      20  
Number of Buses Purchased for Replacment  7      
Reduced Emissions        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Fresno County Rural Transit Agency Jeffrey D. Webster 559-233-6789   jwebster_ruraltransit@fresnocog.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$433 $-46 $387
Non-bond Funding
State/Federal*
$476 $0 $476
 
Total**** $909 $-46 $863

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$909 $-46 $863 $863 $863 $0
 
Total* $909 $-46 $863 $863 $863 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2008 

08/30/2008 
10/23/2009 

10/23/2009 
06/28/2008 

03/16/2009 
95   

 


Begin Closeout Phase

End Closeout Phase
09/30/2008 

10/30/2008 
10/23/2009 

10/23/2009 
08/09/2009 

11/30/2009 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20
Number of Buses Purchased for Replacment 7
Reduced Emissions

Bond Funding Cost
Adopted:
$432,950
Current Approved:
$387,064
Actual Expenditures:
$387,064

Click to view the Semi-Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31