Replacement Older 35' Transit Buses

Description: Purchase 8 new CNG buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings
City
Zip Code
 
Senate District
16
Assembly District 30
Congressional District
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability        
Number of Buses Purchased for Replacment  8      
Reduced Emissions        
Reduced Operating/Maintenance Cost        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Kings COunty Area Public Transit Agency Ronald Hughes 559-582-3211X2696   ron.hughes@co.kings.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$355 $0 $355
Non-bond Funding
State/Federal*
$2,710 $34 $2,744
 
Total**** $3,065 $34 $3,099

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,065 $34 $3,099 $3,099 $3,099 $0
 
Total* $3,065 $34 $3,099 $3,099 $3,099 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2007 

04/01/2008 
 

 
07/01/2007 

04/01/2008 
100   

 


Begin Closeout Phase

End Closeout Phase
05/01/2008 

05/01/2008 
05/04/2010 

05/04/2010 
06/30/2008 

06/16/2009 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability
Number of Buses Purchased for Replacment 8
Reduced Emissions
Reduced Operating/Maintenance Cost

Bond Funding Cost
Adopted:
$355,000
Current Approved:
$355,000
Actual Expenditures:
$355,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31