Replacement of Older Dial-A-Ride Buses

Description: Replace 7 buses w/ new buses - AMENDED to Replaced 10 Dial-A-Ride buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings
City
Zip Code
 
Senate District
16
Assembly District 30
Congressional District
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Decreased Maintenance Cost (percent)  30      
Number of Buses Purchased for Replacment  7      
Useful Life (years)  4      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Kings County Area Public Transit Agency Ronald Hughes 559-582-3211X2696   ron.hughes@co.kings.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$232 $0 $232
PTMISEA-99314
$234 $0 $234
Non-bond Funding
 
Total**** $466 $2 $467

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$466 $2 $467 $467 $467 $0
 
Total* $466 $2 $467 $467 $467 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2008 

03/01/2009 
09/22/2009 

04/29/2010 
09/18/2008 

04/01/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2009 

04/01/2009 
04/29/2010 

04/29/2010 
04/01/2010 

04/23/2010 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Decreased Maintenance Cost (percent) 30
Number of Buses Purchased for Replacment 7
Useful Life (years) 4

Bond Funding Cost
Adopted:
$465,539
Current Approved:
$465,539
Actual Expenditures:
$465,539

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31