Caltrans Logo

Automatic Fare Collection Equipment

Description: Purchase and install automatic fare collection equipment

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings
City Hanford
Zip Code 93232
 
Senate District
16
Assembly District 30
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  15      
Increased Ridership  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RONALD HUGHES (559) 582-3211   RON.HUGHES@CO.KINGS.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$30 $0 $30
PTMISEA-99313
$127 $0 $127
Non-bond Funding
State/Federal*
$543 $-32 $511
 
Total**** $700 $-32 $668

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$700 $-32 $668 $668 $668 $0
 
Total* $700 $-32 $668 $668 $668 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/22/2010 

09/28/2010 
05/16/2011 

05/16/2011 
11/16/2010 

01/27/2011 
 

 


Begin Closeout Phase

End Closeout Phase
03/30/2011 

04/01/2011 
05/16/2011 

05/16/2011 
03/23/2011 

04/04/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 15
Increased Ridership 5

Bond Funding Cost
Adopted:
$156,807
Current Approved:
$127,231
Actual Expenditures:
$127,231

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31