Mid City/Expo LRT Project Phase 1

Description: Expand LR 7.7 miles

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code 90012
 
Senate District
22, 26
Assembly District 46, 47, 48
Congressional District 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 42, 43, 44, 45, 46
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  14    14  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
LA County Metropolitan Transportation Authority Gladys Lowe (213) 922-2459   loweg@metro.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$53,500 $27,970 $81,470
PTMISEA-99314
$0 $56,993 $56,993
Non-bond Funding
State/Federal*
$643,900 $-63,372 $580,528
Local**
$0 $131,697 $131,697
 
Total**** $697,400 $153,288 $850,688

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$23,402 $36 $23,438 $23,438 $23,438 $-0
Design(PS&E)
$16,700 $0 $16,700 $16,834 $16,834 $-134
Right of Way
$24,947 $-10,247 $14,700 $6,959 $6,959 $7,741
Construction
$632,351 $163,499 $795,850 $442,143 $442,143 $353,707
 
Total* $697,400 $153,288 $850,688 $489,375 $489,375 $361,313

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/01/2000 

02/01/2006 
 

 
05/01/2000 

02/01/2006 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/01/2006 

12/01/2009 
 

 
02/01/2006 

12/01/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
02/01/2006 

02/01/2010 
 

01/04/2013 
02/01/2006 

06/01/2013 
99   

 


Begin Construction Phase

End Construction Phase
02/01/2006 

09/01/2012 
 

01/04/2013 
02/01/2006 

06/01/2013 
99   

 


Begin Closeout Phase

End Closeout Phase
11/01/2012 

01/01/2013 
01/04/2013 

01/04/2013 
06/01/2013 

09/01/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 14 14

Bond Funding Cost
Adopted:
$53,500,000
Current Approved:
$138,462,779
Actual Expenditures:
$138,462,779

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31