Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Mid City/Expo LRT Project Phase 1 |
Description: Expand LR 7.7 miles
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Los Angeles |
Zip Code | 90012 |
Senate District |
22, 26 |
Assembly District | 46, 47, 48 |
Congressional District | 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 42, 43, 44, 45, 46 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 14 | 14 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
LA County Metropolitan Transportation Authority | Gladys Lowe | (213) 922-2459 | loweg@metro.net |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$53,500 | $27,970 | $81,470 | ||||
PTMISEA-99314 |
$0 | $56,993 | $56,993 | ||||
Non-bond Funding | |||||||
State/Federal* |
$643,900 | $-63,372 | $580,528 | ||||
Local** |
$0 | $131,697 | $131,697 | ||||
Total**** | $697,400 | $153,288 | $850,688 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$23,402 | $36 | $23,438 | $23,438 | $23,438 | $-0 | |
Design(PS&E) |
$16,700 | $0 | $16,700 | $16,834 | $16,834 | $-134 | |
Right of Way |
$24,947 | $-10,247 | $14,700 | $6,959 | $6,959 | $7,741 | |
Construction |
$632,351 | $163,499 | $795,850 | $442,143 | $442,143 | $353,707 | |
Total* | $697,400 | $153,288 | $850,688 | $489,375 | $489,375 | $361,313 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
05/01/2000 02/01/2006 |
|
05/01/2000 02/01/2006 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/01/2006 12/01/2009 |
|
02/01/2006 12/01/2009 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
02/01/2006 02/01/2010 |
01/04/2013 |
02/01/2006 06/01/2013 |
99 | |
0 0 |
Begin Construction Phase
End Construction Phase |
02/01/2006 09/01/2012 |
01/04/2013 |
02/01/2006 06/01/2013 |
99 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
11/01/2012 01/01/2013 |
01/04/2013 01/04/2013 |
06/01/2013 09/01/2013 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 14 | 14 |
Bond Funding Cost | |
---|---|
Adopted: |
$53,500,000 |
Current Approved: |
$138,462,779 |
Actual Expenditures: |
$138,462,779 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31