Mid City/Expo LRT Project Phase 2 |
Description: Expand Light Rail - Expo Line
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Los Angeles |
Zip Code | 90012 |
Senate District |
23, 26, 28 |
Assembly District | 41, 47, 53 |
Congressional District | 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 42, 43, 44, 45, 46 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additonal Rail Miles | 7 | |
Increased Ridership | 3 | 103 |
Useful Life (years) | 30 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
LA County Metropolitan Transportation Authority | Gladys Lowe | (213) 922-2459 | loweg@metro.net |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$0 | $60,993 | $60,993 | ||||
PTMISEA-99314 |
$0 | $74,990 | $74,990 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $76,059 | $76,059 | ||||
Local** |
$0 | $874,374 | $874,374 | ||||
Total**** | $0 | $1,086,417 | $1,086,417 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $19,989 | $19,989 | $13,602 | $13,602 | $6,387 | |
Design(PS&E) |
$0 | $3,713 | $3,713 | $18,760 | $18,760 | $-15,046 | |
Right of Way |
$0 | $253,701 | $253,701 | $124,932 | $124,932 | $128,769 | |
Construction |
$0 | $809,013 | $809,013 | $928,023 | $928,023 | $-119,010 | |
Total* | $0 | $1,086,417 | $1,086,417 | $1,085,317 | $1,085,317 | $1,100 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2007 12/01/2010 |
03/10/2011 |
01/01/2007 01/01/2010 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/01/2010 07/01/2015 |
03/10/2011 09/04/2018 |
02/01/2010 10/01/2010 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
12/01/2010 07/01/2013 |
03/10/2011 |
02/01/2010 07/01/2013 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
07/01/2010 07/01/2015 |
09/04/2018 09/04/2018 |
03/01/2010 11/01/2015 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
07/01/2015 07/01/2018 |
09/04/2018 09/04/2018 |
02/01/2017 06/01/2019 |
100 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additonal Rail Miles | 7 | |
Increased Ridership | 3 | 103 |
Useful Life (years) | 30 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$135,983,130 |
Actual Expenditures: |
$135,983,130 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31