Caltrans Logo

Purchase of 14 40-foot Buses

Description: Purchase of 14 40-foot transit buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Gardena
Zip Code 90249
 
Senate District
25
Assembly District 51
Congressional District 35
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase in Ridership (percent)  8      
Reduce Emissions (percent)  100      
Reduced Emissions      100  
Useful Life (years)  12      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of Gardena Robert Hildebrand (562) 436-4656   robertinlb@msn.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $22 $22
PTMISEA-99314
$767 $0 $767
Non-bond Funding
State/Federal*
$7,283 $0 $7,283
 
Total**** $8,050 $22 $8,072

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$8,050 $22 $8,072 $789 $789 $7,283
 
Total* $8,050 $22 $8,072 $789 $789 $7,283

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2008 

09/01/2009 
08/18/2009 

08/18/2009 
08/01/2008 

09/01/2009 
50   

 


Begin Closeout Phase

End Closeout Phase
10/01/2009 

12/01/2009 
08/18/2009 

08/18/2009 
09/01/2009 

10/01/2009 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Ridership (percent) 8
Reduce Emissions (percent) 100
Reduced Emissions 100
Useful Life (years) 12

Bond Funding Cost
Adopted:
$767,142
Current Approved:
$767,142
Actual Expenditures:
$767,142

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31