New Bus Operations & Maintenance Facility (Division 13)

Description: Construction of a New Bus Operations & Maintenance Facility (Union Division)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code 90012
 
Senate District
22
Assembly District 46
Congressional District 34
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  8      
Reduced Operating/Maintenance Cost      10  
Useful Life (years)  30      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
LA County Metropolitan Transportation Authority Nela De Castro (213) 922-6166   Decastrom@metro.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $14 $14
PTMISEA-99313
$4,454 $40,669 $45,123
PTMISEA-99314
$539 $7,103 $7,642
Non-bond Funding
State/Federal*
$0 $53,250 $53,250
Local**
$1,900 $12,427 $14,327
 
Total**** $6,893 $113,463 $120,356

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$4,900 $-4,397 $503 $302 $302 $201
Design(PS&E)
$514 $10,925 $11,439 $8,619 $8,619 $2,820
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$68,786 $39,628 $108,414 $43,843 $43,843 $64,570
 
Total* $6,893 $113,463 $120,356 $52,765 $52,765 $67,591

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/2006 

09/30/2008 
08/28/2009 

09/03/2010 
09/01/2006 

09/01/2010 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2008 

01/01/2010 
08/28/2009 

03/10/2011 
12/01/2008 

10/01/2010 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2010 

12/31/2011 
03/08/2012 

09/04/2014 
03/01/2010 

05/01/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2012 

08/30/2012 
03/01/2017 

03/01/2017 
02/01/2017 

02/28/2017 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 8
Reduced Operating/Maintenance Cost 10
Useful Life (years) 30

Bond Funding Cost
Adopted:
$4,992,816
Current Approved:
$52,764,816
Actual Expenditures:
$52,764,816

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31