Clean Fuel Bus Replacement

Description: Purchase 40 new buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Montebello
Zip Code 90640
 
Senate District
30
Assembly District 58
Congressional District 38
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  6    50  
Useful Life (years)  12      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of Montebello, Montebello Bus Lines Miriam Castaneda (323) 887-4625   mcastaneda@cityofmontebello.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $54 $54
PTMISEA-99314
$1,517 $854 $2,371
Non-bond Funding
State/Federal*
$22,897 $-747 $22,150
 
Total**** $24,414 $161 $24,575

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$24,414 $161 $24,575 $2,425 $2,425 $22,150
 
Total* $24,414 $161 $24,575 $2,425 $2,425 $22,150

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2007 

10/01/2009 
 

 
05/01/2007 

10/01/2009 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2009 

12/01/2009 
05/12/2011 

05/12/2011 
04/01/2010 

02/01/2011 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 6 50
Useful Life (years) 12

Bond Funding Cost
Adopted:
$1,516,625
Current Approved:
$2,370,983
Actual Expenditures:
$2,370,983

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31