Caltrans Logo

Rolling Stock Spare Parts

Description: Procurement of Rotem & Bombardier passenger car spare parts, Motive Power locomotive parts, design and procure locomotive related equipment parts, testing & integration.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code 90012
 
Senate District
18, 19, 20, 21, 22, 23, 24, 25, 27, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38
Assembly District 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 48, 49, 50, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80
Congressional District 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 42, 43, 44, 45, 46
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Decreased Maintenance Cost (percent)  10      
Extend Vehicle Life (years)  30      
Increase System Reliability      1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
LA County Metropolitan Transportation Authority Frank Flores (213) 922-2456   floresf@metro.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $61 $61
PTMISEA-99314
$2,500 $-600 $1,900
Non-bond Funding
 
Total**** $2,500 $-539 $1,961

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,500 $-539 $1,961 $1,961 $1,961 $0
 
Total* $2,500 $-539 $1,961 $1,961 $1,961 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/01/2008 

10/01/2009 
 

08/20/2019 
02/01/2008 

01/01/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2009 

06/01/2010 
08/20/2019 

08/20/2019 
02/01/2018 

06/01/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Decreased Maintenance Cost (percent) 10
Extend Vehicle Life (years) 30
Increase System Reliability 1

Bond Funding Cost
Adopted:
$2,500,000
Current Approved:
$1,900,000
Actual Expenditures:
$1,900,000

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31