Caltrans Logo

Keller Street Yard

Description: Keller Street Yard improvements

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code 90012
 
Senate District
18, 19, 20, 21, 22, 23, 24, 25, 27, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38
Assembly District 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 48, 49, 50, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80
Congressional District 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 42, 43, 44, 45, 46
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      11  
Reduced Operating/Maintenance Cost  25      
Useful Life (years)  50      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
LA County Metropolitan Transportation Authority Frank Flores (213) 922-2456   floresf@metro.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99314
$5,660 $0 $5,660
Non-bond Funding
State/Federal*
$5,266 $1,421 $6,687
Local**
$1,032 $0 $1,032
 
Total**** $11,958 $1,421 $13,379

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$626 $0 $626 $5,401 $5,401 $-4,775
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$11,332 $1,421 $12,753 $5,102 $5,102 $7,651
 
Total* $11,958 $1,421 $13,379 $10,502 $10,502 $2,877

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

12/08/2007 
 

 
 

12/08/2007 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
02/01/2008 

02/01/2009 
04/13/2010 

09/14/2011 
09/13/2009 

02/18/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
02/01/2009 

06/01/2009 
02/24/2012 

02/24/2012 
12/15/2011 

04/30/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 11
Reduced Operating/Maintenance Cost 25
Useful Life (years) 50

Bond Funding Cost
Adopted:
$5,659,996
Current Approved:
$5,659,996
Actual Expenditures:
$5,659,996

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31