Purchase 2 Madera Co. MCC Buses

Description: Paratransit vehicles 16-passenger

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Madera
City
Zip Code
 
Senate District
12, 14
Assembly District 25, 29, 31
Congressional District
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase Vehicle Reliability (percent)  83      
Number of Buses Purchased for Replacment  2      
Useful Life (years)  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Madera County Transportation Commission Richard Poythress 559-675-0721   richard@maderactc.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$140 $-2 $138
Non-bond Funding
 
Total**** $140 $-2 $138

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $138 $138 $-138
Construction
$140 $-2 $138 $0 $0 $138
 
Total* $140 $-2 $138 $138 $138 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2008 

09/30/2008 
09/17/2008 

09/17/2008 
09/30/2008 

06/30/2009 
 

 


Begin Closeout Phase

End Closeout Phase
09/30/2008 

09/30/2008 
05/19/2010 

09/17/2008 
05/19/2009 

06/30/2009 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase Vehicle Reliability (percent) 83
Number of Buses Purchased for Replacment 2
Useful Life (years) 5

Bond Funding Cost
Adopted:
$140,000
Current Approved:
$137,550
Actual Expenditures:
$137,550

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31