Caltrans Logo

Madera Co. Amtrak Station Improvements

Description: Construction of improvements to the new Amtrak Station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Madera
City Madera
Zip Code 93637
 
Senate District
12, 14
Assembly District 25, 29, 31
Congressional District 19
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase in Ridership (percent)  10      
Increased Ridership      2  
Useful Life (years)  30      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Madera County Transportation Commission Richard Poythress (559) 675-0721   richard@maderactc.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$604 $-54 $549
Non-bond Funding
State/Federal*
$1,497 $-1,497 $0
Local**
$245 $-245 $0
 
Total**** $2,346 $-1,796 $549

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$95 $-95 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$175 $-175 $0 $0 $0 $0
Construction
$2,076 $-1,526 $549 $549 $549 $0
 
Total* $2,346 $-1,796 $549 $549 $549 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
08/07/2012 

09/25/2015 
02/01/2011 

12/01/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2008 

09/30/2008 
09/25/2015 

09/25/2015 
09/01/2013 

02/19/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
09/30/2008 

09/30/2008 
09/25/2015 

09/25/2015 
02/01/2014 

08/31/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Ridership (percent) 10
Increased Ridership 2
Useful Life (years) 30

Bond Funding Cost
Adopted:
$603,782
Current Approved:
$549,337
Actual Expenditures:
$549,337

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31