Gold Country Stage Bus Stop Improvements

Description: Bus stop upgrades, ADA improvements & accessibility

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Nevada
City Nevada City, Ca
Zip Code 95959
 
Senate District
03
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5    20  
Increased Ridership  5    3  
Reduced Emissions      1  
Reduced Operating/Maintenance Cost      1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SUSAN HEALY-HARMAN (530) 477-0103   SUSAN HEALY-HARMAN@CO.NEVADA.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $24 $24
PTMISEA-99313
$559 $13 $572
PTMISEA-99314
$1 $0 $1
Non-bond Funding
 
Total**** $560 $37 $598

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$560 $37 $598 $598 $598 $0
 
Total* $560 $37 $598 $598 $598 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
03/01/2017 

03/01/2017 
09/01/2015 

06/01/2016 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2011 

10/31/2012 
10/06/2016 

08/29/2020 
06/01/2020 

07/01/2020 
100   

 


Begin Closeout Phase

End Closeout Phase
11/01/2012 

05/31/2013 
03/14/2022 

02/23/2023 
12/31/2021 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5 20
Increased Ridership 5 3
Reduced Emissions 1
Reduced Operating/Maintenance Cost 1

Bond Funding Cost
Adopted:
$560,368
Current Approved:
$573,134
Actual Expenditures:
$573,134

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31