Description: Project will procure 55 buses persuant to the agency's fleet composition plan.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda, Contra Costa |
City | Oakland |
Zip Code | 94612 |
Senate District |
07, 09, 10 |
Assembly District | 11, 14, 16, 18, 20 |
Congressional District | |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Buses Purchased for Replacment | 52 | |
Number of New Buses Purchased for Expansion | 15 | |
Reduced Emissions | ||
Useful Life (years) | 12 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
AC Transit | Kate Miller | (510) 891-4859 | kmiller@actransit.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$2,999 | $-1,277 | $1,722 | ||||
PTMISEA-99314 |
$15,668 | $-4,789 | $10,879 | ||||
Non-bond Funding | |||||||
Local** |
$17,964 | $-17,964 | $0 | ||||
Total**** | $36,631 | $-24,030 | $12,601 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $12,601 | $12,601 | $-12,601 | |
Construction |
$36,631 | $-24,030 | $12,601 | $0 | $0 | $12,601 | |
Total* | $36,631 | $-24,030 | $12,601 | $12,601 | $12,601 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
|
01/12/2012 01/12/2012 |
01/01/2008 06/30/2011 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
01/01/2010 02/01/2010 |
01/12/2012 01/12/2012 |
07/01/2011 10/31/2011 |
100 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Buses Purchased for Replacment | 52 | |
Number of New Buses Purchased for Expansion | 15 | |
Reduced Emissions | ||
Useful Life (years) | 12 |
Bond Funding Cost | |
---|---|
Adopted: |
$18,666,608 |
Current Approved: |
$12,600,813 |
Actual Expenditures: |
$12,600,813 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31