City of Fairfield 35-foot Bus Purchase

Description: Project is to purchase two (2) diesel 35-foot buses for fleet renewal and to reduce costs and pollution.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Solano
City Fairfield
Zip Code 94533
 
Senate District
05
Assembly District 08
Congressional District
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Reduce Emissions (percent)        
Reduced Operating/Maintenance Cost        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of Fairfield Geogre K. Fink (707) 428-7768   gfink@ci.fairfield.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$15 $1 $16
PTMISEA-99313
$400 $0 $400
Non-bond Funding
State/Federal*
$460 $-460 $0
Local**
$0 $342 $342
 
Total**** $875 $-118 $757

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$875 $-118 $757 $757 $757 $0
 
Total* $875 $-118 $757 $757 $757 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2008 

11/01/2008 
05/19/2009 

05/19/2009 
04/01/2009 

05/22/2009 
100   

 


Begin Closeout Phase

End Closeout Phase
11/30/2009 

12/31/2009 
05/19/2009 

04/14/2009 
05/22/2009 

06/22/2009 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduce Emissions (percent)
Reduced Operating/Maintenance Cost

Bond Funding Cost
Adopted:
$414,855
Current Approved:
$415,500
Actual Expenditures:
$415,500

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31