Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
City of Fairfield 35-foot Bus Purchase |
Description: Project is to purchase two (2) diesel 35-foot buses for fleet renewal and to reduce costs and pollution.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Solano |
City | Fairfield |
Zip Code | 94533 |
Senate District |
05 |
Assembly District | 08 |
Congressional District | |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduce Emissions (percent) | ||
Reduced Operating/Maintenance Cost |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
City of Fairfield | Geogre K. Fink | (707) 428-7768 | gfink@ci.fairfield.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$15 | $1 | $16 | ||||
PTMISEA-99313 |
$400 | $0 | $400 | ||||
Non-bond Funding | |||||||
State/Federal* |
$460 | $-460 | $0 | ||||
Local** |
$0 | $342 | $342 | ||||
Total**** | $875 | $-118 | $757 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$875 | $-118 | $757 | $757 | $757 | $0 | |
Total* | $875 | $-118 | $757 | $757 | $757 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
07/01/2008 11/01/2008 |
05/19/2009 05/19/2009 |
04/01/2009 05/22/2009 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
11/30/2009 12/31/2009 |
05/19/2009 04/14/2009 |
05/22/2009 06/22/2009 |
100 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduce Emissions (percent) | ||
Reduced Operating/Maintenance Cost |
Bond Funding Cost | |
---|---|
Adopted: |
$414,855 |
Current Approved: |
$415,500 |
Actual Expenditures: |
$415,500 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31