GGBHTD Body Shop Roof and Skylights Replacement

Description: Project will replace body shop roof and skylights and add solar panels to improve worker safety

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Marin
City San Francisco
Zip Code 94129
 
Senate District
03, 08
Assembly District 06, 12, 13
Congressional District
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Safety Improvement (percent)        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Golden Gate Bridge, Hwy and Trans. District Gayle S. Prior (415) 923-2373   gprior@goldengate.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$414 $0 $414
Non-bond Funding
Local**
$61 $297 $358
 
Total**** $475 $297 $772

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$25 $-25 $0 $79 $79 $-79
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$450 $322 $772 $792 $792 $-20
 
Total* $475 $297 $772 $871 $871 $-99

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2008 

03/01/2008 
03/22/2011 

03/22/2011 
04/30/2009 

06/16/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2008 

11/01/2008 
03/22/2011 

03/06/2012 
06/24/2009 

11/01/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2008 

01/01/2009 
03/06/2012 

03/06/2012 
12/01/2011 

01/01/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Safety Improvement (percent)

Bond Funding Cost
Adopted:
$414,019
Current Approved:
$456,519
Actual Expenditures:
$456,519

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31