Caltrans Logo

LAVTA Route 10 Bus Rapid Transit

Description: Project will provide Bus Rapid Transit along the heavily travelled LAVTA Route 10 -- between the City of Livermore and Dublin/Pleasanton BART station.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Livermore
Zip Code 94551
 
Senate District
09, 10
Assembly District 15, 18
Congressional District
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase in Ridership (percent)  39      
Increased Ridership      39  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Livermore Amador Valley Transit Authority Joe Whitaker (925) 455-7561   jwhitaker@lavta.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $19 $19
PTMISEA-99313
$429 $242 $671
PTMISEA-99314
$268 $151 $418
Non-bond Funding
State/Federal*
$6,894 $-349 $6,545
Local**
$2,581 $-2,483 $98
 
Total**** $10,172 $-2,421 $7,751

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$325 $-325 $0 $0 $0 $0
Design(PS&E)
$2,256 $-2,256 $0 $0 $0 $0
Right of Way
$823 $-823 $0 $0 $0 $0
Construction
$6,768 $983 $7,751 $7,751 $7,751 $0
 
Total* $10,172 $-2,421 $7,751 $7,751 $7,751 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
03/27/2012 

03/27/2012 
11/01/2007 

02/01/2009 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2007 

03/01/2008 
 

08/06/2010 
02/01/2009 

11/01/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2008 

01/01/2009 
01/06/2010 

01/06/2010 
11/01/2009 

08/01/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2009 

01/01/2009 
03/27/2012 

03/27/2012 
08/01/2010 

10/01/2010 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Ridership (percent) 39
Increased Ridership 39

Bond Funding Cost
Adopted:
$696,915
Current Approved:
$7,751,056
Actual Expenditures:
$7,751,056

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31