NCTPA Hybrid Bus Purchase

Description: Project is to fund the purchase of one (1) gasoline/electric hybrid bus (out of 4 bus procurement)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Napa
City Napa
Zip Code 94559
 
Senate District
02
Assembly District 07
Congressional District
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Reduce Emissions (percent)        
Reduced Emissions        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Napa County Transportation and Planning Agency Tracy Geraghty (707) 259-8779   tgeraghty@nctpa.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $13 $13
PTMISEA-99313
$300 $0 $300
Non-bond Funding
State/Federal*
$2,518 $-1,239 $1,279
Local**
$0 $113 $113
 
Total**** $2,818 $-1,113 $1,705

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,818 $-1,113 $1,705 $1,705 $1,705 $0
 
Total* $2,818 $-1,113 $1,705 $1,705 $1,705 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2002 

07/31/2008 
04/14/2009 

04/14/2009 
03/01/2002 

11/16/2008 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2007 

06/01/2008 
03/16/2010 

03/16/2010 
01/01/2008 

07/01/2009 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2008 

12/01/2008 
03/16/2010 

03/16/2010 
06/01/2009 

06/30/2009 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduce Emissions (percent)
Reduced Emissions

Bond Funding Cost
Adopted:
$300,170
Current Approved:
$300,170
Actual Expenditures:
$300,170

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31