Bond Accountability
SFMTA Overhead Rehabilitation 5 Fulton / 21 Hayes |
Description: Project is to rehabilitate the overhead contact system (OCS) along the 5-Fulton and 21-Hayes tolley lines.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Francisco |
City | San Francisco |
Zip Code | 94103 |
Senate District |
03, 08 |
Assembly District | 12, 13 |
Congressional District | |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | |
Increase System Reliability (percent) | ||
Reduced Operating/Maintenance Cost | 2 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
San Francisco Municipal Transportation Agency | Joel Goldberg | (415) 701-4499 | joel.goldberg@sfmta.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$3,000 | $-3,000 | $0 | ||||
PTMISEA-99314 |
$0 | $2,267 | $2,267 | ||||
Non-bond Funding | |||||||
State/Federal* |
$16,700 | $-248 | $16,452 | ||||
Local** |
$4,173 | $-2,257 | $1,916 | ||||
Total**** | $23,873 | $-3,237 | $20,636 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$1,000 | $-200 | $800 | $0 | $0 | $800 | |
Design(PS&E) |
$2,000 | $313 | $2,313 | $16,194 | $16,194 | $-13,881 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$20,873 | $-3,350 | $17,523 | $4,442 | $4,442 | $13,081 | |
Total* | $23,873 | $-3,237 | $20,636 | $20,636 | $20,636 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
05/01/2006 12/01/2007 |
|
05/01/2006 12/01/2007 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/01/2008 06/01/2009 |
08/16/2010 08/16/2010 |
11/01/2007 04/30/2010 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
07/01/2009 12/01/2010 |
08/07/2014 08/07/2014 |
05/17/2010 12/10/2012 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
01/01/2010 07/01/2011 |
08/07/2014 08/07/2014 |
01/01/2013 04/01/2013 |
100 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | |
Increase System Reliability (percent) | ||
Reduced Operating/Maintenance Cost | 2 |
Bond Funding Cost | |
---|---|
Adopted: |
$3,000,000 |
Current Approved: |
$2,267,054 |
Actual Expenditures: |
$2,267,054 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31