Caltrans Logo

SFMTA Geneva Yard - Historic Street Car Enclosure Facility

Description: Project is to construct a car enclosure facility to protect historic light rail streetcars at the SFMTA Geneva yard

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City San Francisco
Zip Code 94103
 
Senate District
03, 08
Assembly District 12, 13
Congressional District
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Extend Vehicle Life (years)        
Reduced Operating/Maintenance Cost      70  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
San Francisco Municipal Transportation Agency Joel Goldberg (415) 701-4499   joel.goldberg@sfmta.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$7,500 $-1,408 $6,092
Non-bond Funding
State/Federal*
$2,626 $-126 $2,500
Local**
$1,025 $629 $1,654
 
Total**** $11,151 $-906 $10,246

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$245 $0 $245 $245 $245 $0
Design(PS&E)
$650 $427 $1,077 $1,080 $1,080 $-3
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$10,256 $-1,333 $8,924 $8,920 $8,920 $3
 
Total* $11,151 $-906 $10,246 $10,246 $10,246 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/31/2001 

03/01/2002 
 

 
07/31/2001 

03/01/2002 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2002 

07/31/2008 
08/07/2014 

08/07/2014 
04/01/2002 

12/01/2007 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2008 

03/01/2010 
08/07/2014 

08/07/2014 
11/17/2008 

02/08/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2010 

09/01/2010 
08/07/2014 

08/07/2014 
02/09/2012 

06/30/2013 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Extend Vehicle Life (years)
Reduced Operating/Maintenance Cost 70

Bond Funding Cost
Adopted:
$7,500,000
Current Approved:
$6,091,855
Actual Expenditures:
$6,091,855

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31