Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
SFMTA Farebox Rehabilitation |
Description: Project will modernize SFMTA's fleet fareboxes making it easier for customers to pay fares.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Francisco |
City | San Francisco |
Zip Code | 94103 |
Senate District |
03, 08 |
Assembly District | 12, 13 |
Congressional District | |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 20 | |
Percent of existing system Modernized | 100 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
San Francisco Municipal Transportation Agency | Joel Goldberg | (415) 701-4499 | joel.goldberg@sfmta.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $45 | $45 | ||||
PTMISEA-99314 |
$20,000 | $-410 | $19,590 | ||||
Non-bond Funding | |||||||
Total**** | $20,000 | $-366 | $19,634 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$20,000 | $-366 | $19,634 | $19,634 | $19,634 | $0 | |
Total* | $20,000 | $-366 | $19,634 | $19,634 | $19,634 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
03/03/2008 02/28/2009 |
08/06/2014 08/06/2014 |
05/17/2010 12/10/2012 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
03/30/2009 03/01/2010 |
08/06/2014 08/06/2014 |
12/11/2012 04/01/2013 |
100 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 20 | |
Percent of existing system Modernized | 100 |
Bond Funding Cost | |
---|---|
Adopted: |
$20,000,000 |
Current Approved: |
$19,589,906 |
Actual Expenditures: |
$19,589,906 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31