Caltrans Logo

Bus Rehabilitation

Description: Mechanical and/or electrical system rehabilitation work for 35 standard 40' Neoplan coaches and 27 articulated 60' coaches

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City San Francisco
Zip Code 94103
 
Senate District
12, 13
Assembly District 03, 08
Congressional District
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  1    19  
Reduced Operating/Maintenance Cost  1    19  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ELIAS GIRMA (415) 701-4634   ELIAS.GIRMA@SFMTA.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$250 $-27 $223
Non-bond Funding
 
Total**** $250 $-27 $223

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$250 $-27 $223 $223 $223 $0
 
Total* $250 $-27 $223 $223 $223 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2011 

08/31/2011 
09/02/2014 

09/02/2014 
11/19/2012 

07/01/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2011 

03/31/2012 
08/18/2015 

09/30/2015 
08/01/2014 

12/30/2015 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 1 19
Reduced Operating/Maintenance Cost 1 19

Bond Funding Cost
Adopted:
$250,000
Current Approved:
$223,237
Actual Expenditures:
$223,237

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31